Quebrada Azul Parcels — Tejona, Tilarán
Line extension · HDPE · ASADA

Quebrada Azul Parcels — Tejona, Tilarán

2,400 mHDPE pipeline 150 mm
₡87.0MCFIA valuation
In progressASADA/ORAC reception
Documented case · Tilarán, Guanacaste

Tejona: 2.4 kilometers where there was never water

The longest extension in RAM's record — 2,400 meters of 150 mm HDPE bringing potable water to an area historically without coverage.

Project area in Tejona, Tilarán
01
The starting point

An area off the water map

Property owners in Tejona and Santa Rosa de Tilarán had no potable water coverage: without a network, no availability letters or building permits were possible.

Technical studies proved feasibility and a water capacity letter was obtained from ASADA Parcelas Quebrada Azul, endorsed by the ORAC — conditioned on building the new infrastructure.

0water coverage before the project
HDPE pipe installation
02
The engineering

HDPE for 2.4 kilometers of demanding terrain

The design chose 150 mm high-density polyethylene (HDPE) — a 2,400-meter line, RAM's longest recorded project, with a CFIA valuation of ₡87.0 million (code 1188299).

Complete hydraulic design, plans, and APC-CFIA processing, in coordination with the ASADA as system operator.

2,400 mof 150 mm HDPE — RAM's record
Tejona pipeline works progress
03
The construction

Technical direction end to end

RAM held the technical direction of the works: construction supervision, compliance control against approved plans, and coordination of tests and inspections.

All under the community operator's scheme: an ASADA receiving works of this scale demands the same documentary rigor as AyA.

₡87.0 MCFIA valuation of the works
Completed works in Tejona
04
The outcome

Formal water where there was none

The project enables service through formal infrastructure approved by the ASADA and the ORAC, with final reception in process.

For an area that historically lived without coverage, the difference isn't a case file: it's properties that can develop with formal potable water for the first time.

ORACinstitutional endorsement

Our longest project, in the most forgotten area

2,400 meters of HDPE bringing water where it never reached. If your property is outside the coverage area, the answer isn't waiting for the network — it's building it, with the ASADA and ORAC as allies.

2,400 mRAM's longest extension
150 mmhigh-density HDPE
₡87.0 MCFIA valuation
1stformal coverage for the area
Request assessmentAsk on WhatsApp

Construction gallery

Technical data

Tubería2.400 m PEAD 150 mm
Código CFIA1188299
Tasación₡86.952.600
OperadorASADA Parcelas Quebrada Azul
MaterialPolietileno de alta densidad (PEAD)
UbicaciónTejona, Tilarán, Guanacaste