El Salto — Manuel Antonio, Quepos
Denied availability → pipeline under construction

El Salto — Manuel Antonio, Quepos

1,615 mPVC pipeline 150 mm
2regulating valves
From denialto work under construction

The challenge

The project had received negative water availability responses and dragged a tangled easement unresolved for years: survey plans that did not close, pending topographic corrections and a stalled file at AyA.

The RAM solution

RAM took the complete case: corrected the easement topography until AyA approved it, designed the 1,615 m line with two regulating valves (CFIA-sealed drawings), renewed the water capacity certificates and used the legal route when the file went dormant.

The result

The denials became a viable project: the work is under construction today to secure the water availability. The clearest proof that an institutional “no” can be reversed with engineering and persistence.

Construction gallery

Technical data

Tubería1.615 m PVC SDR26/17 de 150 mm
AccesoriosDos válvulas reguladoras de 100 mm
ServidumbreCaso complejo resuelto con correcciones topográficas ante AyA
Vía legalRecurso de amparo para destrabar el expediente
EstadoEn construcción (2025-2026)
ClienteDesarrollador, Manuel Antonio / Quepos

Facing a similar challenge?

Let's talk about your project. The initial assessment is free.

Other projects

Big Door Prize — Quepos

Big Door Prize — Quepos

A foreign developer in Manuel Antonio needed potable water, but the connection required 2.2 km of pipeline, crossing a national ro

View full case
GranSol — Esparza

GranSol — Esparza

A social-interest subdivision in Esparza needed its complete potable water network, with the quality standards and tests AyA requi

View full case
🗨