San Miguel: turnkey pipeline with easement
200 meters of pipe, materials supply, pressure tests, and interconnection — the complete package for a residential development.

AyA's requirements on the table
The residential development needed supply infrastructure and compliance with AyA's technical and legal requirements, including an easement to formalize the system.
The owner needed a single point of responsibility from start to finish: design, materials, works, and institutional management.

Materials, works, and tests from one team
Hydraulic design, plans, APC-CFIA (code 1114617, valuation ₡15.0 million), certified materials supply, construction under technical direction, and pressure testing.
The same turnkey scheme as RAM's larger works, applied at residential-development scale.

Interconnected; easement in progress
The infrastructure was built and interconnected to the potable water system, meeting AyA's technical requirements.
The easement in favor of AyA advances in constitution — the last link to close the system's full formalization.
One responsible party, zero loose ends
Design, materials, construction, tests, and interconnection from one team — with the easement managed as part of the package. That's how a pipeline is delivered without surprises.