WhatsAppFree assessment
Quintas Natura — San Mateo
Line extension · Country-lot development

Quintas Natura — San Mateo

285 mPVC pipeline 150 mm
1easement constituted
100%delivered to AyA

The challenge

A country-lot development in San Mateo needed to secure potable water with a 150 mm line extension and the corresponding easement.

The RAM solution

RAM executed the full package: design, right-of-way and pipeline easement, construction of the 285 meters and file management before AyA's regional office.

The result

Work delivered to AyA's satisfaction. Proof the turnkey model works just as well on mid-size projects.

Construction gallery

Technical data

Tubería285 m PVC SDR26 de 150 mm
ServidumbreDe paso y tubería constituida
Código APC625912
UbicaciónSan Mateo, Alajuela
ClienteR A S Asesores S.A. (Quintas Natura)

Facing a similar challenge?

Let's talk about your project. The initial assessment is free.

Other projects

Big Door Prize — Quepos

Big Door Prize — Quepos

A foreign developer in Manuel Antonio needed potable water, but the connection required 2.2 km of pipeline, crossing a national ro

View full case
GranSol — Esparza

GranSol — Esparza

A social-interest subdivision in Esparza needed its complete potable water network, with the quality standards and tests AyA requi

View full case
🗨