Palmas Pacífica: the third project of a returning client
1,888 meters of pipe with a relief valve, an easement in progress, and current water capacity letters. The project that confirms an international developer's trust.

Formalize to consolidate
The development needed to formalize its supply infrastructure and regularize the easements to meet AyA's requirements and consolidate access to potable water.
The client wasn't new: the same developer behind Big Door Prize, who after that project trusted RAM again — first here, then with Rickdonna.

1,888 meters with pressure control
Complete hydraulic design, plans, and APC-CFIA processing (code 1095504) for a 1,888-meter, 100 mm PVC line, including a 100 mm relief valve for system control.
CFIA valuation of ₡33.0 million and case file FAM-8141 before AyA, with permanent institutional coordination and follow-up.

Easement and current water capacity
The constitution of the easement in favor of AyA advances as an integral part of the project, along with institutional follow-up of the file.
The project's water capacity letters have been kept current — including their 2025 renewal — so the development never loses its position with the operator.

Client loyalty as the metric
In infrastructure consulting, the most honest indicator isn't a number: it's the client coming back. Three consecutive projects from the same international developer — Big Door Prize, Palmas Pacífica, and Rickdonna — tell that story.
The project advances in formalizing its water supply per AyA's requirements, documented even with 2025 drone footage.
The client who came back — twice
1,888 meters designed and processed, current water capacity, and an international developer who has entrusted three consecutive projects. That's how long-term relationships are built — with the right engineering.