ASADA Juanilama Technical Study
Technical study · ASADA · Hydraulic modeling

ASADA Juanilama Technical Study

~10 kmnetwork surveyed
ASADAJuanilama
In progresswith AyA
Documented case · Esparza, Puntarenas

ASADA Juanilama: the study that ordered the future

Ten kilometers of network surveyed, pumping tests, water balance, and projections — the comprehensive technical study that tells an ASADA how much it can grow.

ASADA Juanilama system
01
The starting point

Growing without knowing how far

The ASADA needed to determine its system's real capacity to back future availability letters and plan its growth — the technical requirement AyA imposes on every community operator that wants to grant new services.

Without that study, every availability letter granted was a blind bet on the source and the network.

~10 kmof network to survey and model
Field survey of the network
02
The field

Surveying the entire network with GNSS

RAM surveyed close to ten kilometers of network — pipes, valves, tanks, and sources in a single georeferenced spatial model.

Pumping tests and spring gauging were coordinated to establish the sources' real production: the number that rules any growth decision.

GNSScomplete georeferenced survey
Technical work on the ASADA study
03
The analysis

Balance, modeling, and future demand

With the system digitized, the water balance, hydraulic modeling, and supply-demand analysis with population projections were developed.

It also included managing the Villamar de los Campos easement — because RAM's studies don't stay on paper: they also unblock the related files.

25 yearsplanning horizon
Documented ASADA system
04
The deliverable

A report that answers before AyA

The technical study evaluates the system's current and future capacity per AyA's requirements, with professional reports, observation responses, and technical coordination before the institution.

Today the board decides on numbers, not intuition — and the study is a reference in RAM's certified track record.

100%of the system modeled and documented

An ASADA that decides with numbers

Network surveyed, sources measured, demand projected, and a report that answers before AyA. If your ASADA needs to know how much it can grow, this is the path — and there's a free calculator on this site to start today.

~10 kmof network surveyed
25 yearsof demand projection
1easement managed along the way
CFIAprofessionally signed report
Request assessmentAsk on WhatsApp

Construction gallery

Technical data

AlcanceEstudio técnico de sistema de abastecimiento
RedLevantamiento de ~10 km
MétodosPruebas de bombeo, balance hídrico, modelación hidráulica
AnálisisOferta y demanda, proyecciones de crecimiento
OperadorASADA Juanilama
Período2024-2026

Facing a similar challenge?

Let's talk about your project. The initial assessment is at no cost.